Trade Contractor Outreach Events – Southern Approach, Package B

The Frederick Douglass Tunnel is the centerpiece of this program, featuring two new tunnel tubes serving primarily MARC and Amtrak passengers. The new tunnel is named in honor of Frederick Douglass, a Maryland native and an early leader in the fight for the rights of women and minorities. He was also a frequent railroad passenger after escaping to his freedom by boarding a train in Baltimore.

Clark Construction and Stacy and Witbeck (CSW) are committed to assembling a diverse team of trade partners to deliver a significant enhancement for the Northeast Corridor, B&P Tunnel Replacement Program, featuring the new Frederick Douglass Tunnel – Southern Approach.

Join us at our events to:

  • Connect with the CSW team
  • Gain insight into the project’s scope and schedule
  • Learn about our pre-qualification process

Project Details

This package includes construction work located in the southern approach to two new high-capacity tunnels, including the corridor from the West Baltimore MARC Station to the tunnel portals.

Package B – Multiple Guaranteed Maximum Price (GMP) Proposals

Anticipate 5 GMP Opportunities

GMP Updated Bid Schedule

  • GMP 1 – In Progress
  • GMP 2 – Current Opportunity
  • GMP 3 – Anticipated Early 2026

GMP 2 – Scope

  • Design Package D (Partial) – Wilkens Interlocking
  • Design Package O2A/O2B – Edmondson Temporary Bridge & Utilities
  • Design Package P (Partial) – Southbound MARC Station Platform & Core and Shell
  • Design Package O1 (Partial) – Franklin Avenue Bridge
  • Design Package G2 – Franklin Avenue
  • Design Package J – Lafayette Bridge
  • Design Package I (Partial) – South Approach Structure 
  • Design Package P2 – Lot B Bus Loop

2025 Dates:​

Jul 7th, 2025 – Pre-Bid Conference / Outreach Event (In-Person)

July 10th, 2025 – RFI Deadline​

July 24th, 2025 – GMP 2 proposals due to CSW JV